Power works and underground of the network is fully complete. All overhead lines and poles along the alignment have been decommissioned and removed including across the rail alignment.
Chorus and Fibre works are almost complete and being cut over next week.
Watermain works have all been procured and will be being competed during night works during November.
Sewer design and timing is being worked through collaboratively with designers and council. Further update on timing and updated anticipated dates to be updated.
We will continue to accomodate the cruise ships into the Picton area and 2 way traffic over weekends and extended periods for the local Picton Community and visitors when it is safe to do so.