Updates

Update 14/11/2022

Power works and underground of the network is fully complete. All overhead lines and poles along the alignment have been decommissioned and removed including across the rail alignment.

Chorus and Fibre works are almost complete and being cut over next week.

Watermain works have all been procured and will be being competed during night works during November.

Sewer design and timing is being worked through collaboratively with designers and council. Further update on timing and updated anticipated dates to be updated.

We will continue to accomodate the cruise ships into the Picton area and 2 way traffic over weekends and extended periods for the local Picton Community and visitors when it is safe to do so.

Update 21/10/2022

Works are progressing well. We are currently continuing with the power and communications packages and anticipate having this commissioned on 8th November 2022, overhead lines removed shortly after that.

The Watermain and Sewer works in the middle of the road we expect to begin these shortly and anticipate this being completed prior to Christmas where we will re-open the road.

Dublin Street Site Office